Railroad Street crossing fix with STC
The city and South Texas College will split the cost of fixing the rough railroad crossing on Railroad Street — about $60,365 total. Waiting on STC's board to sign.
Westgate Drive signal synchronization
Six traffic signals along Westgate Drive from the Expressway to Old 83 will be modernized and synchronized using $609,335 in federal safety funds — aimed at cutting the long backups drivers face at peak hours. The city is on the hook for any overruns.
18th Street repaving
A one-mile mill-and-overlay of 18th Street is going out to bid, with the city aiming to schedule construction during the Christmas school break to spare Memorial School traffic.
Citywide Pavement Condition Assessment
Seven street segments across town will be repaved, including 8th, 10th, Esplanada, Palmas and Pino Streets, with the 10th Street segment extended to cover Bridge to Utah. Residents on those streets should see smoother roads soon.
Boundary Road Paving Partnership with Mercedes
Weslaco and Mercedes signed a framework to split costs on paving shared boundary roads, starting with Mile 2 1/2 West Road. Each project still comes back to the Commission for a specific vote, and Mayor Gonzalez stressed no city money moves until all parties pay their share.
Sugarcane Drive road closure hurting small business
A coffee shop owner told the Commission her sales dropped ~80% after both access roads closed with little notice. The mayor directed staff and the EDC to meet with her and look at help.
Interstate 2 frontage road flooding between Texas Boulevard and Westgate
Only about three ditches connect to I-2 across the whole corridor, so neighborhood water bottlenecks at the frontage roads — stranding drivers and threatening hospital access during storms. TxDOT and the city plan to explore detention ponds and new drainage connections.
Traffic Safety on 10th and 11th Streets (Jolene Subdivision)
Forty-five residents are asking, for the third time, for speed bumps, completed sidewalks, and warning lights on 10th and 11th Streets, where about 950 vehicles a day speed past — including Weslaco East students. A 2023 speed study was done but the data was never provided, and nearby Garden Terrace got speed bumps and a 20-mph limit.
18th Street and Milanos Road intersection safety
A crash-prone intersection is getting a $28,725 traffic study, with commissioners noting frequent accidents and the future Weslaco loop possibly routing down Milanos by 2034.
Westgate & 18th intersection study
The congested Westgate/18th intersection will get a $54,900 traffic study to determine whether a signal or other improvements are warranted — a step toward making the project grant-ready.
Mid-Valley Airport drainage project
An interlocal with the county drainage district gets surveying, environmental and drainage design done in-house at lower cost, clearing the way for the runway extension funded by an $8 million legislative appropriation.
Hospital Service Road naming
The road between Isaac Rodriguez Park and Knapp Medical Center gets one official name — Hospital Service Road — ending confusion among Google, 911 and appraisal district records. It stays a private road the city won't maintain.
Pike Road reconstruction
Pike Road — a key industrial corridor — gets a full rebuild design, not just a repave, fixing misaligned storm inlets and drainage problems along the way. Funded by 2025 bonds.
Neighborhood Street Paving Near Library
Four streets — Illinois, 5th, Oregon, and Gray Lane — will be repaved for up to $200,000, with work phased around the library construction. Oregon and Gray Lane could start within weeks.
Pike & VoTech roundabout and traffic congestion
The city is asking the feds for $5.4 million — with zero local match — to build the Vo-Tech & Pike roundabout. The price nearly doubled from earlier estimates because of underground utilities and a switch to concrete.
6th Street and Airport Drive traffic congestion
Everyone hates this intersection. A $15,114 change order moves signal upgrades there, with AI-based signal timing, and staff is meeting with TxDOT to sync the lights with the highway signals.
Cemetery culvert safety hazard
The culvert crossing at Weslaco Cemetery is literally splitting — a 4-inch gap with the ground collapsing. Engineering interns designed the fix: new pipe, wider road, guardrail. Construction awaits approval and cost estimates.