Summary
The Utah Street roadway cutting through the park turned out too deteriorated to simply resurface, so the Commission approved up to $93,080 to rebuild it. Work will be phased one side at a time so Boys and Girls Club buses keep getting through.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Aug 4, 2026.
Impact analysis
Up to $93,080 added to the park project.
Park visitors and Boys and Girls Club families using the improved roadway.
Mentions & discussions (1)