A design mistake left an electrical junction box too far from the lift station for the floats to work — a $16,750 change order fixes it so the contractor can be released.
At a glance
- Total mentions
- 2
- Last 30 days
- 1
Last discussed Jun 2, 2026.
Impact analysis
$16,750 added to the project cost.
Sewer service customers near Torritos and Illinois relying on the lift station.
No groups negatively affected
Mentions & discussions (3)
City Commission - Nov 3, 2026
An emergency sewer repair near Bridge and Agostadero needs retroactive approval after work was awarded to OMT Utilities for $66,500.
City Commission - Jun 2, 2026
A design mistake left an electrical junction box too far from the lift station for the floats to work — a $16,750 change order fixes it so the contractor can be released.
Weslaco crews repair major water line break, service restored
Weslaco crews repair major water line break, service restored ValleyCentral.com
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Weslaco
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.