Reservoir levels are historically low at 27%, but both plants passed TCEQ inspection at 100% compliance. Floodwater moving down from upstream could raise levels — and bring water into local levees.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 15, 2026.
Impact analysis
Multiple ongoing capital projects; the reservoir rehab may draw a $21 million zero-match grant.
All residents who rely on the city's water and wastewater service.
Low reservoir levels (26%) signal ongoing drought risk for the water supply.
Mentions & discussions (4)
City Commission - Sep 15, 2026
For $514,980, engineers will map every water line, sewer line, lift station, and plant — and build a 10-year priority list. The city currently fixes things reactively, and this study should also unlock state and federal grant money.
City Commission - Aug 18, 2026
A new $99,266 trailer will exercise and GPS-map water valves so crews can find them in emergencies — a response to past overlays that buried valves and a recent leak that wasted 650,000 gallons. Inframark also explained the recent citywide pressure drop was caused by a power outage and generator failure.
City Commission - Jul 21, 2026
Reservoir levels are historically low at 27%, but both plants passed TCEQ inspection at 100% compliance. Floodwater moving down from upstream could raise levels — and bring water into local levees.
City Commission - Apr 15, 2026
Inframark reported both wastewater plants removing 98% of contaminants with no violations, reservoirs at just 26% capacity, Lift Station 12 back online, and safety fixes at exposed lift station wells — with Lift Station 20 repairs next out for bid.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Weslaco
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.